Back

Installation on an EPC basis of plants connected to the Large Hadron Collider

Client
Cern
Scope of work
EPC contract for mechanical installation, E&I and LHC equipment
Resources
92
Technical details

Creation of the cooling system, installation of heat exchangers, cooling towers, centrifugal pumps and expansion vessels.

3800 valves and 55 km of cable were installed.

Total hours worked: 500,000