Steam turbine installation

Client
Eni S.p.A.
Scope of work
EPC contract for the installation of a steam turbine at the Mantua Refinery
Resources
100
Technical details

Prefabrication and assembly of 30 tonnes of piping. Installation of 182 valves and 37 tonnes of structures. Laying of 15 km of electrical cables. Plant commissioning and start-up.